19/04 TEPCO must provide more solid information on recovery from nuclear crisis


In this image released Saturday, April 16, 2011, by Tokyo Electric Power Co., top of the container of the nuclear reactor, painted in yellow, of Unit 4 at the Fukushima Dai-ichi Nuclear Plant is observed from its side with a T-Hawk drone Friday, April 15, 2011 in Okuma, Fukushima Prefecture, northeastern Japan. (AP Photo/Tokyo Electric Power Co.)
In this image released Saturday, April 16, 2011, by Tokyo Electric Power Co., top of the container of the nuclear reactor, painted in yellow, of Unit 4 at the Fukushima Dai-ichi Nuclear Plant is observed from its side with a T-Hawk drone Friday, April 15, 2011 in Okuma, Fukushima Prefecture, northeastern Japan. (AP Photo/Tokyo Electric Power Co.)
Layout of cooling systems at Fukushima No.1 Power Plant. (Mainichi)
Layout of cooling systems at Fukushima No.1 Power Plant. (Mainichi)

Just when will people be able to breathe a sigh of relief that the crisis at the Fukushima No. 1 Nuclear Power Plant is over? The lives of residents living around the plant are hanging on an answer to this question. For local farmers and businesses, it is a matter of life and death.

Tokyo Electric Power Co. (TEPCO)'s announcement of a schedule for bringing the disaster under control was significant. Unfortunately, however, the schedule lacks concrete details. Rather than serving as a plan to solve the crisis it is a display of just how many difficulties remain.

Radioactive materials continue to leak from the plant's reactors, but the source of the leaks and the exact times materials have leaked remain unclear. To control the leaks, the reactors must be cooled to under 100 degrees Celsius and stabilized -- a process known as a "cold shutdown."

TEPCO's schedule says it will take six to nine months for reactors to be brought to a cold shutdown. But when looking squarely at the schedule, it seems unlikely that the process will be completed within this time frame. A year is probably more realistic.

In this image released by Tokyo Electric Power Co., a radio-controlled PakBot robot opens a door inside the reactor building of Unit 2 as it is monitored with another Pakbot from behind during inspection of the tsunami-damaged facilities at the Fukushima Dai-ichi Nuclear Power Plant Monday, April 18, 2011 in Okuma, Fukushima Prefecture, northeastern Japan.
In this image released by Tokyo Electric Power Co., a radio-controlled PakBot robot opens a door inside the reactor building of Unit 2 as it is monitored with another Pakbot from behind during inspection of the tsunami-damaged facilities at the Fukushima Dai-ichi Nuclear Power Plant Monday, April 18, 2011 in Okuma, Fukushima Prefecture, northeastern Japan.

The power company says that it will first drench the containment vessels of the plant's No. 1 and 3 reactors -- including the pressure vessels -- in water. But if the containment vessels are damaged, water will leak out. Drenching the containment vessels in water is something that has not been done before when handling a nuclear power plant accident, and workers must be well aware of the strength of containment vessels.

But even if this first stage goes well, a cold shutdown will not immediately follow. Water must be circulated in a closed loop to continually remove heat from the nuclear fuel.

The containment vessel of the No. 2 reactor has almost certainly been damaged. Plans to patch up the damage have been drawn up, but radiation levels around the reactor must first be reduced. Because of this, it remains unclear if such work will actually be possible. And even if another device to continually remove heat from the fuel is built, unforeseen problems could occur.

TEPCO should form plans to address each of these issues while taking alternative solutions into consideration, and produce a concrete appraisal of the situation. In doing so, it is vital to confirm the state of damage to the nuclear reactors and pipes. Which parts are damaged and what is the extent of the damage? Workers may not be able to view every part up close, but TEPCO should provide solid information on each possibility.

Overall there has been a lack of information regarding the nuclear power plant. We still don't know the amount of radioactive materials that continue to leak from the power plant. TEPCO's schedule says it will expand and enhance its monitoring of radiation within three months, but the company should make an effort to speed this process up and do its job of releasing information. Otherwise, residents will find it difficult to draw up plans for their futures.

This Sunday, April 10, 2011 photo released by Tokyo Electric Power Co. (TEPCO) shows orange colored floats suspending
This Sunday, April 10, 2011 photo released by Tokyo Electric Power Co. (TEPCO) shows orange colored floats suspending"silt fence," that was installed under water to help prevent contaminated water from spreading outside the Fukushima Dai-ichi nuclear power plant's bay. (AP Photo/Tokyo Electric Power Co.)

The process of bringing a nuclear power plant accident under control must be measured in years, not months. The work to achieve a solution must be shared, and a system to handle the crisis over the long term must be developed. The release of detailed information will form the pillars of these efforts.

(Mainichi Japan) April 19, 2011


20/04 余録:「工程」の今後

 歩くという単純な行動も水の中では思い通りにならない。戦場での行動を重い液体の中での運動にたとえたのは、先日も小欄で引いたクラウゼビッツの「戦争論」だ。敵情が分からない戦場では思わぬ事態が次々に予定された行動を阻む▲あらかじめ考え抜いた必勝の戦術も、不確実性が液体のように満ちた戦場では必ず齟齬(そご)をきたし、もくろみは狂ってしまう。似た状況は戦争だけに限らない。およそ平時には予想できなかった深刻な危機にあって、物事は人間の思い通りに運ばないのが世の常である▲目標は遠いが、はっきりしている。そこに至るおおまかな道筋はようやく描かれた。だが、まとわりつく不確実性はその歩みを妨げようとする……福島第1原発事故の収束に向けて示された原子炉安定化の工程表のことだ▲東京電力はきのう2号機から出た高濃度の汚染水を貯蔵施設に送る作業を始めた。まずは一歩である。だが、その前日には4号機の建屋地下の水深20センチと見られた汚染水の深さが実は5メートルだったことが判明した。前に踏み出す足にまとわりつく予想外の展開である▲原子炉安定までの「6~9カ月」は避難を強いられている住民には気の遠くなるほど長かろう。だが専門家の多くはむしろ工程表の見通しは甘いともいう。一刻も早い収束は至上命令だが、不測の事態続発も覚悟せねばならぬ人類未踏の原発災害収拾の道のりである▲ここはまとわりつく不確実性を封じる周到な情報収集と、思わぬ変事への機敏な対応が求められる現場だ。また社会的な不確実性を封じる方策も忘れてはならない。国民への徹底した情報公開である。

毎日新聞 2011年4月20日 0時13分

19/04 余録:悲しいランドセルの春

 <あなたはちいさい肩に/はじめて/何か、を背負う/机に向かってひらく教科書/それは級友全部と同じ持ちもの/なかには/同じことが書かれているけれど/読み上げる声の千差万別>。石垣りんさんの詩「ランドセル」は続ける▲<入学のその翌日から/ほんの少しずつ/あなたたちのランドセルの重みは/違ってくるのだ/手を貸すことの出来ない/その重み/かわいい一年生よ。>--成長と共に子供たちそれぞれの重みを蓄えていくランドセルだ。常ならば、それが喜びに跳ねる春である▲だがこの春はいったい何度泥にまみれたランドセルに胸を詰まらせればいいのか。児童多数が津波にのまれた宮城県の小学校近くに積まれた色とりどりのランドセルの写真は正視できなかった。テレビ報道でがれきの中から見つかるランドセルの名札も涙ににじんだ▲その被災地の悲しみも癒えないというのに、18日朝は栃木県鹿沼市の国道脇に土に汚れたランドセルがいくつも積まれた光景に胸を突かれることになった。こちらはまごうことなき人災、小学校4~6年生の6人の列にクレーン車が突っ込み、児童全員が亡くなった▲多くの子供を連れ去った災害の非情に打ちひしがれていたところで、今度は人の不注意がもたらした子供たちの理不尽な死である。「なぜ」と、事故を起こした運転者をことさら厳しく問い詰めたくなるのは人情だ。天に生かされる命を実感する今だからこそ悔しい▲ランドセル一つ一つに蓄えられていく子供らそれぞれの未来だ。それを奪い去るあらゆるまがまがしい力から子供を守らねばならない。改めてそう誓いたい。

18/04 余録:異国の地で

 東日本大震災の1週間後、神戸港から中国の天津に向かうフェリーは日本脱出を急ぐ留学生など中国人であふれ返っていた。ざわめきの中で間瀬弘樹さんは被災地の知人たちの安否を気遣いつつ、「今は私を待つ大地へ」と41歳の自分を励ました▲5日後にたどり着いたのは北京の西方約560キロ、内モンゴル自治区のクブチ砂漠に位置する恩格貝だ。91年以来、「日本沙漠緑化実践協会」がボランティアを募って植林を進めてきた。間瀬さんは駐在員として毎年3月下旬から7カ月半をここで過ごす▲砂漠に苗木を植える「緑の協力隊」の参加者には東北地方の人も多い。その面々と顔見知りの中国人スタッフが「あの人は無事かな」と気をもむ。村人たちも心配する。しばらくすると、津波で亡くなったり家を流された被災者の情報が入ってきた▲3月下旬に来るはずだった「緑の協力隊」は計画を取り消した。5月には来訪予定があるが、その後の派遣を断念したグループもある。300万本以上の木を植えて緑野を広げ、中国側から高く評価されてきた活動は最大の試練に直面している▲だが間瀬さんに迷いはない。未来のために砂漠に木を植える。それは黄砂による日本の環境汚染防止にも役立つ。この活動を始めた砂地農業の権威、故・遠山正瑛氏の口癖は「やればできる。やらなければできない」だった。その気概を受け継ぐ覚悟を決めている▲以上は国際電話で聞いた話だ。大震災と津波が今も広げ続けている無数の波紋の一つである。直接の被災者はもちろん、多様な厳しい試練の渦中にいるすべての人々に、心の底から声援を送りたい。

毎日新聞 2011年4月18日 0時10分

19/04 福島第1原発:「県民への風評被害」是正 玄葉国家戦略相


玄葉光一郎国家戦略担当相
玄葉光一郎国家戦略担当相

 福島県選出の玄葉光一郎国家戦略担当相は19日午前の閣僚懇談会で、東京電力福島第1原発事故で福島県民のホテルなどへの宿泊予約が拒否されるなど「人への風評被害」が起きているとし、「各省で業界の指導など、やれることを精いっぱいやってほしい」と述べ、差別的な行為の是正に取り組むよう求めた。

 玄葉氏は「他県に福島ナンバーの車が止まっていると『どけ』と言われ、避難している子供が『放射能がついている』と言われる」と実例を紹介。閣議後の記者会見で「一部の心ない対応は本当に残念でならない」と指摘した。

 枝野幸男官房長官は会見で福島県民に対する差別的対応について「明らかに過剰な反応だ。避難している(福島)県民や、安全が確認されている福島県産品を温かく受け止めてほしい」と呼びかけた。【田中成之】

毎日新聞 2011年4月19日 12時45分(最終更新 4月19日 15時47分)


19/04 福島第1原発:放射線証明の提示要求を撤回 つくば


福島県からの被災後の転入者に放射線検査を求めた、つくば市の内部文書(一部画像を処理しています)=2011年4月19日、安味伸一撮影
福島県からの被災後の転入者に放射線検査を求めた、つくば市の内部文書(一部画像を処理しています)=2011年4月19日、安味伸一撮影

 東京電力福島第1原発事故で福島県から避難してきた転入者に対し、茨城県つくば市が放射線量検査(スクリーニング)を求める措置を決め、抗議を受けて撤回していたことが分かった。市原健一市長が19日に会見し「対応に不備があり誤解を生じた。被災者への配慮が足りず本当に申し訳ない」と陳謝した。

 転入届の窓口の市職員が11日、放射線量検査済み証明書の提示を求めたため発覚。市は即日、福島県からの転入者に検査を求める措置を撤回した。3月14日に福島県からの避難者受け入れを始めたのに合わせ避難所などで検査を実施し、同17日付で転入者にも検査を求める措置を決めていた。

 放射線医学総合研究所(千葉市)の神田玲子・放射線防護研究センター上席研究員は「エックス線診断を受けた人から放射線がうつることがないのと同じで人からの汚染はない」と話した。【安味伸一】

毎日新聞 2011年4月19日 21時29分(最終更新 4月19日 21時57分)


19/04 福島第1原発:伊が原発再開を断念 国民投票前に反対強く

 イタリア政府は19日、同国の原発再開に関する議論を無期限で凍結することを上院に伝えた。これまでは凍結期間を1年間としていた。事実上、再開を断念したとみられる。福島第1原発の事故を受けて反対世論が高まり、再開の是非を問う6月の国民投票での敗北が懸念されていた。

 これで6月12、13日に予定されていた国民投票は実施されない公算が大きくなった。イタリア政府は3月23日、原発再開の候補地選定などについて1年間、議論を凍結することを決めていた。

 イタリアは旧ソ連のチェルノブイリ原発事故を受けて1987年に国民投票で原発廃止を決定。しかしエネルギー需要の80%以上を輸入に頼っていることから、ベルルスコーニ政権は再開方針を表明。ことし1月、憲法裁判所が野党の求めに応じて国民投票実施を認める判断を下した。(共同)

19/04 asahi - 天声人語 - Buồn ơi! chào mi

2011年4月19日(火)付

 災害のときに誰もが案じるのは大切な人の消息だ。声を聞くまで、姿を見るまでは、心ここにあらずとなろう。関東大震災で大勢が避難した東京・上野公園では、一番目立つ西郷さんの像に、尋ね人の張り紙が何百枚も張られたという▼上野のお山は身内や知人を捜す声が昼夜絶えなかった。「深更(しんこう)の二時三時頃には、全山の其(その)叫び声が寝耳に徹して、何とも云(い)ひ知られぬ悲痛の感に打たれた」と、ジャーナリストの宮武外骨(がいこつ)は書き残した。生きてあれと願う必死の声、声、声で、山全体がうなったのである▼東北には今も、大切な人を捜して叫び続ける方が大勢いる。1面にある「被災者数」の欄は、発生から38日たってなお行方不明の人は1万を超す。奇跡という言葉さえ遠ざかり、「せめて無縁仏にはしたくない」と語る涙に胸がつぶれる▼岩手県山田町では、ともに後継ぎ息子をさらわれた漁師2人が、海へ出て捜している。2人の妻は毎朝避難所を抜け出し、岸で名を呼んで泣いていると小紙記事にあった。喪にも服せぬ人の多さに津波の酷を思う▼漁師は「避難所の人は表で笑っているけど、皆そんな気持ち。俺らもそうだ」と言う。おそらく被災地の「喪の途(みち)」は只事(ただごと)でなく長いのだ。復興のかけ声に虚(うつ)ろな人を、置き去りにしては進めない▼被災した人が一人になったときの顔への、想像力を失うまい。震災前の日本は「待つこと」の苦手な社会になっていた。最も歩みの緩やかな人を見失わない復興が、いまは大切だ。

19/04 原発工程表―これ以上悪くせず前へ

 「長い闘い」の長さが、数字で見えてきた。福島第一原発の事故収束をめぐって、東京電力が発表した工程表である。

 3カ月くらいかけて、事故炉や燃料プールを安定して冷却できるようにする。その後3~6カ月ほどで、炉を冷温停止状態に落ち着かせる。

 原発周辺の人々の生活再建はさらに長い闘いになるが、その前提である放射能源の制圧だけでも6~9カ月かかることを、東電は初めて認めた。

 福島第一の1~4号機は今、炉やプールに水を注ぎ続けることで小康が保たれている。これが破綻(はたん)したら、放射性物質のさらなる大量放出の恐れが高まり、周辺地域の避難のあり方を再び見直すことにもなろう。

 そうなれば、住民が背負う重荷は今の比ではない。

 こうしたなかでの収束作戦である。なによりも強く求められているのは、これ以上悪い状態にしない、ということだ。

 まず備えるべきは、不測の出来事だ。とりわけ怖いのは、先日の大きな余震のときのように外部電源が途絶え、注水が止まることである。

 工程表も余震や落雷などのリスクに触れ、外部電源系の補強を考えているようだ。この対策は急務といえよう。

 事故収束に向けた作業は、近づいて中をのぞくことのできない炉やプールを相手にする。工程を一歩進めるごとに見直しを迫られるのは必至だ。

 期限にばかり気をとられて急ぐあまり、大きな問題点を見逃すことがあってはならない。

 工程表を見て気にかかるのは長丁場に必要な人力だ。

 2号機格納容器の密閉や、4号機の燃料プール周辺の補強など難しい作業が列挙されているが、それらにどれだけの作業員がかかわるのだろうか。

 現場は、放射線を浴びる危険が大きい。1号機建屋の入り口では、作業員が1時間いるだけで被曝(ひばく)線量限度を超える放射線が測定された。工程表にも「放射線レベルの高い場所で、作業が長期化する恐れ」が明記されている。同じ人にずっと働いてもらうわけにはいかない。

 さらに、放射能源を封じなくてはならないのは1~4号機のすべてで、これらの作業を同時に進めなくてはならない。

 東電や原子炉メーカー、関連会社の人たちだけでは、とても追いつかないかもしれない。

 応援を含め、要員をどうやって確保するか。一線で働く人たちの健康をどう守っていくか。

 政府も、この工程表を受け入れる以上は責任が重い。

19/04 TEPCO aims for cold shutdown in 6-9 months, but no guarantees


2011/04/19

このエントリをはてなブックマークに追加 Yahoo!ブックマークに登録 このエントリをdel.icio.usに登録 このエントリをlivedoorクリップに登録 このエントリをBuzzurlに登録

photoTEPCO Chairman Tsunehisa Katsumata, right, and Executive Vice President Sakae Muto discuss the company's strategy to deal with the nuclear crisis on April 17. (Hiroshi Kawai)

Editor's note: We will update our earthquake news as frequently as possible on AJW's Facebook page:http://www.facebook.com/AJW.Asahi. Please check the latest developments in this disaster. From Toshio Jo, managing editor, International Division, The Asahi Shimbun.

* * *

Tokyo Electric Power Co. has presented a two-stage scenario to stabilize the crippled Fukushima No. 1 nuclear power plant, but it is unclear whether its goals can be achieved as scheduled.

At least six months will be needed to achieve a cold shutdown of the reactors, which means bringing core temperatures under 100 degrees, according to the company's road map announced April 17.

In the first step, which will take about three months, TEPCO plans to cool the reactors in a stable manner and cap the amount of radioactive materials released.

In the second step, expected to be completed in six to nine months, the company aims to achieve cold shutdown and substantially reduce the amount of radioactive materials.

Industry minister Banri Kaieda said April 17 that the government plans to decide whether evacuees who were living in areas from around the Fukushima plant can return home after TEPCO's second step ends in six to nine months.

The government plans to review evacuation zones at that time after consulting with the Nuclear Safety Commission of Japan.

But TEPCO Chairman Tsunehisa Katsumata suggested the road map is only a list of all conceivable measures to deal with the crisis.

"There is no guarantee that we will be able to carry out the plan 100 percent," he said April 17. "We want to start with whatever we can do and cool the reactors successfully."

The key goal is to stabilize the reactors and storage pools for spent fuel rods, which have been releasing radioactive materials.

According to TEPCO, the risk of hydrogen explosions continues at reactors No. 1, 2 and 3, which have been cooled just enough to keep temperatures from rising to dangerous levels.

Nitrogen has been injected into the No. 1 reactor's containment vessel. In the first step of the road map, it will also be injected into the No. 2 and 3 reactors.

Water will also be poured into the containment vessels to cool the pressurized vessels that contain the fuel rods in a stable manner.

In the second step, TEPCO aims to restart circulating cooling systems to achieve a cold shutdown of the reactors.

Radioactive steam is still leaking from the containment vessels at the No. 1 and 3 reactors. TEPCO must locate and plug the leaks before the containment vessels are filled with water.

According to TEPCO, the No. 2 reactor will require additional work because its containment vessel was damaged and highly radioactive water is still flowing out.

While the company plans to close the damaged parts with cement, identifying those parts will be difficult.

In addition, the suppression pool connected to the containment vessel was likely damaged in a hydrogen explosion. Large amounts of highly radioactive water will flow into the ocean if water is poured into the containment vessel.

TEPCO therefore plans to seal the areas around the suppression pool with cement to prevent water leakage.

TEPCO aims to restore regular circulating cooling systems for the fuel storage pools at reactors No. 1, 3 and 4, where pumping trucks have been pouring in water from the outside.

A normal cooling system is already in operation at the No. 2 reactor.

According to TEPCO, the No. 4 reactor's fuel storage pool is vulnerable to earthquakes because of damage to the lower sections of the walls of the reactor building that support the pool.

In the first step, concrete supports will be installed at the bottom of the storage pool to bolster its anti-quake strength. The cracks in the lower parts of the walls will also be sealed.

TEPCO said it cannot yet tell when work can begin on anti-quake reinforcements.

In the road map's second step, a circulating cooling system will be restored while water trucks are deployed to pour water into the pool.

Over the midterm, TEPCO hopes to remove fuel rods from the pool, but specific methods to safely remove and store the damaged fuel rods have yet to be worked out.

The road map also aims to contain the release of radioactive materials into the atmosphere and the ocean.

In the first step, tanks and other facilities will be installed to store highly radioactive water found in the basements of the turbine buildings and outdoor trenches.

In the second step, the reactor buildings will be covered with special sheets.

An estimated 60,000 tons of highly radioactive water is in the basements of the turbine buildings alone.

TEPCO plans to move the contaminated water to a 30,000-ton central waste processing facility at the plant and install temporary tanks to store 12,000 tons by late April.

The water will also be moved to an offshore floating structure provided by the Shizuoka city government that can hold 10,000 tons.

The company also plans to set up a water treatment facility to remove radioactive materials using filters and flocculation agents.


19/04 被災地の美術館や図書館救え 学芸員らが情報サイト

2011年4月19日21時50分

 東日本大震災で被災した公共アーカイブを救え、と全国の学芸員、図書館司書らが情報サイト(http://savemlak.jp/wiki/SaveMLAK)を立ち上げた。

 被災した施設の状況を共有し、施設の復旧や展示物の修復に向けて協力できる専門技能をもったボランティアの派遣につなげるのが狙い。

 19日現在、掲載されているのは、北海道から関東甲信越までの博物館・美術館(823件)、図書館(930件)、文書館(45件)、公民館(71件)。地図や自治体名、施設名から検索ができ、施設ごとに建物の損壊状況や図書・展示物の被害状況が閲覧できる。閲覧者が書き込んで、情報を更新することもできる。

 サイトには、被災地外の学芸員や司書らが支援できる内容を書き込んだり、被災施設側が支援を求める内容を書き込んだりできるコーナーを設けた。

 サイトの運営者側は、避難所での読み聞かせ活動や、車を利用した移動図書館なども企画している。

 運営者有志は23日午後1時から、学習院大学(東京都豊島区)の南3号館203教室で、緊急討議「東日本大震災 被災支援とMLAK いまわたしたちにできることは」を開く。問い合わせはアカデミック・リソース・ガイドの岡本真さん(070・5467・7032)。(阿久沢悦子)

19/04 音楽喫茶、避難所で再オープン 支援の蓄音機、希望の曲

写真:蓄音機を前にした冨山勝敏さん=岩手県陸前高田市、緒方写す拡大蓄音機を前にした冨山勝敏さん=岩手県陸前高田市、緒方写す

 「小さな喫茶店」「お富さん」などの懐かしい曲に、コーヒーの香り。1千人以上が避難する岩手県陸前高田市立第一中学校に、津波で流された音楽喫茶が復活した。休日限定のオープン。きっかけは、東京から送られてきた蓄音機だった。

 「さあ、始めましょうか」。17日午後5時。2階の教室で、「h.イマジン」店長の冨山勝敏さん(69)が蓄音機のハンドルを回した。

 約10人の被災者が、特製のブレンドコーヒーを片手に、体を小刻みに揺らし、曲に合わせて口ずさむ。そんな様子を冨山さんは笑顔で見つめながら、次のレコードを手に取った。約1時間、「青いカナリア」や「俺は待ってるぜ」など、10曲以上の懐かしい曲が次々と流れた。

 冨山さんは市街地でジャズ喫茶を経営していた。地震発生時、客5人を避難させ、高台へ逃げた。津波警報がけたたましく鳴っていた。「海が目の前にあるようだったよ。引き潮に自分の店が流されていくのを見た」

 同中学で避難生活に入った。3月29日、取材に来たテレビカメラの前で「喫茶店も全部なくしてしまったが、めげずに頑張りたい」と話した。「嘆いている場合ではない。何かできないか」と思ったという。

 冨山さんの言葉は、その番組をたまたま見ていた東京都国分寺市の音楽制作者、野口眞一郎さん(59)の心を動かした。4月9日、同中学を訪れ、冨山さんに蓄音機とレコード約50枚を手渡した。

 冨山さんは避難所で日曜日の夕方、1時間限定での店の再開を決心。学校の許可を得た。同年代の人が特にショックを受けているように見え、懐メロを選んで流した。「若かりし頃の曲を聴いて、元気を取り戻して、復興に向かってもらえれば」という願いからだ。冨山さん自身、また店を構えることを目標にしている。

 訪れた永田まき子さん(57)は家と母を津波に流され、とても音楽を聴く気になれなかった。それでも「知ってる曲を久しぶりに聞いて、和みましたし、明るい気持ちになりました」と涙をぬぐった。冨山さんは陸前高田市や大船渡市の避難所を回り、音楽喫茶を臨時開店していく予定だ。(緒方雄大)


19/04 原発作業の恐怖「まるで宇宙空間」 スリーマイル経験者

写真:「ストレスは大変なものだった」。スリーマイル島原発の同僚作業員たちと記念につくったTシャツや当時の識別票を前に語るリチャード・レッシュさん=米ペンシルベニア州、田中写す拡大「ストレスは大変なものだった」。スリーマイル島原発の同僚作業員たちと記念につくったTシャツや当時の識別票を前に語るリチャード・レッシュさん=米ペンシルベニア州、田中写す

写真:スリーマイル島原発の放射能除去作業の際、リチャード・レッシュさんは防護服に身を包み、バルブ室に入った。インスタントカメラで撮った写真の日付は1980年6月13日とあった=本人提供拡大スリーマイル島原発の放射能除去作業の際、リチャード・レッシュさんは防護服に身を包み、バルブ室に入った。インスタントカメラで撮った写真の日付は1980年6月13日とあった=本人提供

写真:スリーマイル島原発は現在も稼働中だ。対岸には、32年前に事故があったことを伝える看板が立つ=米ペンシルベニア州ミドルタウン、田中写す拡大スリーマイル島原発は現在も稼働中だ。対岸には、32年前に事故があったことを伝える看板が立つ=米ペンシルベニア州ミドルタウン、田中写す

 収束の兆しが見えない福島第一原発事故。米国で最悪といわれる1979年のスリーマイル島原発事故をくぐり抜けた電力会社の作業員や住民にとっては、決してひとごとではない。32年前を振り返りながら、懸命に作業を続ける福島の人たちにエールを送る。

 「福島の作業員は、現代のサムライだ。彼らは、自らの寿命が縮まる恐怖を抱きながら、作業をしているはずだ」。米東部ペンシルベニア州のサスケハナ川の中州にあるスリーマイル島原発から車で2時間の自宅で、リチャード・レッシュさん(73)は「サムライ」という言葉を繰り返した。

 レッシュさんは当時、原発を運営していた電力会社の送電部門の作業員だった。原発の知識は全くなかったが、1週間の研修を受け、事故から約2カ月後の5月から原発施設の放射性物質の除去作業に入った。志願に基づいていたため、「給料は全然、変わらなかった」。年齢制限や家族構成などの条件もなかったという。

 放射能から身を守る防護服での作業は、困難を極めた。あらゆるつなぎ目をテープで保護するため、装着するのに40分ぐらいかかる。20キロ近い氷を入れたベストを付けたこともある。特殊なマスクでは、普通の8割ぐらいしか息ができない。視野も狭く、同僚作業員との会話もできない。

 そして、薄い防護服の外は見えない放射能で充満しているという恐怖が常につきまとい、自分の心臓の音が聞こえたように感じた。「まるで宇宙空間での作業だった」。嘔吐(おうと)して窒息しそうになったり、閉所恐怖症でパニックになったりした同僚もいた。「なんで俺はこんなことをしてるんだ」と何度も思った。

 被曝(ひばく)量を抑えるため、1回当たりの作業は最長でも30分程度に制限された。ただ、4週間作業して4週間休むというシフトが約2年間、続いたものの、どれだけ被曝したのか、会社から聞いたこともないし、その後の健康被害の調査も受けたことがない。「今さら、考えても仕方がない」

 幸い、いまのところ体に異変はないという。しかし、「我々の場合は、放射能で汚染された場所が限られていたが、福島は範囲が広いように見える。彼らの方が恐怖心は大きいはずだし、身体に影響が出るのではないか」と心配する。

 スリーマイル近くの住民も「福島」の行く末が心配でならない。25キロ離れた州都ハリスバーグで、市民団体のエリック・エプスタインさん(51)は、毎日、原発周辺の放射能を監視する。「スリーマイル、チェルノブイリ、そして福島に共通するのは、政府や電力会社からの情報は頼りにできないということだ。ここで再び事故があるとは思いたくないが、自ら、情報を入手する手段は持っておきたい」と話していた。

 スリーマイルはいまも稼働する。近くの対岸を訪れると、蒸気をはき出す二つの巨大な冷却塔の隣に、下部の鉄骨がむき出しになったままの冷却塔が二つ並んでいるのが見える。(米ペンシルベニア州ミドルタウン=田中光)

     ◇

 〈スリーマイル島原発事故〉1979年、ポンプ故障などで冷却水が失われ、炉心が溶融。8キロ以内の幼児と妊婦に避難、16キロ以内に屋内退避が勧告され、1週間余り後に解除された。放射性ヨウ素の放出は限定的で、住民の推定被曝量は健康影響が無視できる程度とされたが、炉心に相当の損傷があったため「レベル5」(施設外へのリスクを伴う事故)と認定された。

19/04 高汚染水移送は長期戦 受け皿施設補修、漏水警戒

図:高濃度汚染水の処理拡大高濃度汚染水の処理

図:集中廃棄物処理施設での貯水拡大集中廃棄物処理施設での貯水

 福島第一原発2号機の坑道やタービン建屋地下にある高濃度の放射能汚染水の本格的な移送作業が19日始まった。漏れれば周辺を汚染したり、作業員が被曝(ひばく)するだけに、作業には細心の注意が求められ、当面、移送するのは一部にとどまる。汚染水は浄化して別の場所に保管したり再利用したりする計画で、全てを抜き取り終わるまでには時間がかかりそうだ。

 2号機の坑道では、汚染水がたまって水位が上がっており、抜き取らないと十数日で外部へあふれ出るおそれがある。坑道とつながるタービン建屋地下にたまっている汚染水も、原子炉冷却のための電源復旧工事の妨げになっている。両者合わせて2万5千トンの汚染水があるとみられる。

 移送が始まったのは、坑道のたて坑の汚染水。東電は約1万トンを敷地内の集中廃棄物処理施設へ移す。最初の4分の1は1台のポンプで様子を見ながらくみ上げ、その後3台に増やす。移し終えるのは5月14日ごろがめどになる。19日午後6時現在でたて坑の水位に変化はないというA。

 この汚染水は表面線量が毎時1千ミリシーベルト超。近づくと吐き気や嘔吐(おうと)の症状が出るほど高い放射量だ。移し替えの途中で漏れると、辺りが一気に汚染される。東電原子力・立地本部の松本純一本部長代理は記者会見で「万が一にも漏れがあってはならない」と繰り返してきた。

 移送にはホースを使う。東電は集中廃棄物処理施設まで約800メートル、ホースを引いた。そのほとんどは、2~4号機のタービン建屋内を通した。屋外の作業員の被曝を防ぐとともに、もし漏れても建屋内にとどめるためだ。外に出る部分も余震で揺すられて外れないよう、鋼材で脇を固めたり、溝の中にいれたりした。

 ホースのつなぎ目は金具のほかに針金で硬く縛り、ビニール袋で包んだ。万一漏れた場合に備えて、放射性物質の吸着材の袋を巻き付けた。

 移送された汚染水が集中廃棄物処理施設から周囲に漏れ出す危険を減らすため、施設内のひびやすき間を止水し、建物の耐震性も改めて確認した。さらに、汚染水の水位は地下水位より50センチ程度低く抑えることにした。周囲から水圧がかかって漏れ出しにくくなるためだ。

 施設の容量をフル活用すれば3万トンが入るが、一部を使うにとどめたため、2万5千トンの汚染水を一度に全量移送することはできなくなった。

 東電によると、移送された水は、放射能を減らす浄化処理をした上で別のタンクに貯蔵したり炉心の冷却に再利用したりする。浄化には、放射性物質を沈殿させて集めたり、放射性物質のセシウムを吸着するゼオライトを使ったりする水処理システムの構築が検討されている。

 このほか東電は19日、6号機のタービン建屋地下にしみだしてたまったとみられる地下水100トンを復水器に移送したことを明らかにした。

19/04 High levels of radiation at 2 reactors

The Yomiuri Shimbun

High levels of radiation were measured Sunday by remote-controlled robots inside the buildings that house reactors Nos. 1 and 3 of the Fukushima No. 1 nuclear plant--levels that would need to be lowered for workers to work inside the buildings, the Nuclear and Industrial Safety Agency said Monday.

The agency said radiation levels were measured from 10 to 49 millisieverts per hour for the No. 1 reactor and from 28 to 57 millisieverts per hour for the No. 3 reactor.

"As things stand now, it would be difficult to send workers inside them to work. We need to lower the radiation levels or block them somehow," said Hidehiko Nishiyama, a spokeman for the agency.

It marked the first time that radiation levels have been measured inside the buildings housing reactors Nos. 1 and 3 since hydrogen explosions occurred in these two units in the wake of the massive quake and tsunami on March 11.

Tokyo Electric Power Co., which operates the crisis-hit plant, used two U.S.-made robots to take the measurements.

Measurements at the No. 3 reactor, taken between 11:30 a.m. and 2 p.m. Sunday, found that the temperature inside was from 19 C to 22 C, the humidity from 32 percent to 35 percent, and the oxygen content of the air inside 21 percent.

At the No. 1 reactor, where measurements were taken between 4 p.m. and 5:30 p.m., the temperature ranged from 28 C to 29 C, the humidity from 49 percent to 56 percent, while the oxygen content was 21 percent.

Inside the building housing reactor No. 3, the interior of which was also photographed by a robot Sunday, there was a large amount of debris found, making it impossible for the robot to advance further.

===

N-policy to be verified

Prime Minister Naoto Kan on Monday told a Diet session, held to discuss issues concerning the recent quake, tsunami and nuclear crisis, that the government needs to review its nuclear power policy right from the fundamentals.

Regarding the government's future nuclear policy in light of the latest accident at the Fukushima plant, Kan said: "We need to take all preconceived ideas and go back to the drawing board to examine from the ground up the reasons why the accidents occurred. When we've reached a certain point, we would like to make a thorough verification."

When asked what specific issues were to be verified, Kan said, "The issue of the spent fuels being stored as they were [in the pool inside the reactor building], without there being a proper, systematic framework in place with regard to such issues as the nuclear fuel cycle and final disposal site."

Meanwhile, TEPCO President Masataka Shimizu apologized before the members of the House of Councillors Budget Committee, where he appeared as an unsworn witness, for the recent spate of accidents at the Fukushima No. 1 nuclear plant.

"I would like to sincerely apologize once again for causing so much trouble and anxiety to the residents near the power plant, the people in Fukushima Prefecture and the public at large over the extremely serious matter of radioactive material leaking outside the plant," said Shimizu.

During the upper house committee meeting, Kan rejected the view that the government failed to respond appropriately to the twin disasters and ensuing nuclear plant accident in the inital stages, and that Kan's leadership came into question.

"It is not correct to say that the government's initial response was insufficient. I believe we have been responding to the issues in a sufficient manner," Kan said.

Regarding the timetable for bringing the nuclear crisis at the plant under control, announced by TEPCO on Sunday, Kan said, "The government will do its utmost in cooperating with work undertaken by TEPCO, taking an approach in which we will do whatever we can as the state, so that the timetable presented by TEPCO can be realized as soon as possible."

(Apr. 19, 2011)